Amid growing public backlash to the rapid buildout of data centers across Texas, Gov. Greg Abbott on Monday announced a moratorium on the approval of data centers until regulatory agencies can audit proposed data centers seeking connection to the state's electric grid.
It is unclear how long the audit will take, but Abbott is asking the Public Utility Commission of Texas and the Electric Reliability Council of Texas to ensure data center developers provide information on tax breaks they will receive; power use and generation; water use and cooling operations; efforts to reduce impacts on local communities; and ownership of the facility.
Any projects that fail Abbott's ordered "comprehensive verification and audit" should be denied connection to the grid, the governor said.





Comments