HOUSTON, Texas (KTRK) -- The Texas Commission on Environmental Quality (TCEQ) has resumed approving data center permits before a community impact review ordered by Gov. Greg Abbott is finished, raising questions from watchdog groups about whether the state followed through on its commitment to pause the process.

RELATED: Gov. Greg Abbott directs Texas environmental commission to halt all data center permits, office says Abbott directed the TCEQ to pause permits on Sept. 21 in a letter that also said data center projects must cover all electrical infrastructure costs, result in lower residential electrical bills, and complete audits by ERCOT and the Texas Water Development Board.

But on Wednesday, the TCEQ said it has resumed its normal permit review processes, citing a notification that ERCOT had gathered information for the community impact review for pending data center projects.