HomeLocal NewsBirdwell Lane Reconstruction Remains on Schedule Despite Weather Delays and Unexpected ProblemsBirdwell Lane Reconstruction Remains on Schedule Despite Weather Delays and Unexpected ProblemsMon, November 23, 2026 by KBest News SHARE NOW BIG SPRING, Texas - Despite weather-related delays, waterline breaks, and an unexpected underground erosion problem, Big Spring officials say the $3. 2 million Birdwell Lane reconstruction project remains on schedule to be completed by March 23, 2027.
City of Big Spring Public Works Director Shane Bowles told KBEST Media that he still expects to meet the original 260-day construction timeline, despite several setbacks in recent months.
"The contractors still believe they can hit that deadline," Bowles said, adding that the roadway is expected to be completely reopened with construction finished by March 23.